1 June 2022
Brickwork is finished
9th floor internal units plastering is 50 % complete.
Walkways on 6th are getting tiled. External plastering is 50% complete.
Scaffolding on the internal walkways have started to come down
1 June 2022
Brickwork is finished
9th floor internal units plastering is 50 % complete.
Walkways on 6th are getting tiled. External plastering is 50% complete.
Scaffolding on the internal walkways have started to come down
1 March 2022
10th-floor brickwork has started.
8th-floor plastering has started.
The 4th-floor cupboard and finishes are at 80% complete.
External plastering has started.
The concrete structure is 100% complete.
See below images taken from the site this week.
1 February 2022
Brickwork starting on 9th floor
Plastering finished on 6th floor
Painting in underway inside the units
Tiling and cupboards have started on 4th floor.
See below images taken from the site this week.
1 November 2021
Our dedicated team of professionals has been hard at work ensuring that we are well on schedule, despite a harsh winter. The building structure is at roof level and we’ve just had our first experience of how truly magnificent the views are from each apartment. The roof slab will be completed by the end of the year and internal brickwork in the apartments has been completed up to the 6th floor, with the 7th now underway.
See below images taken from the site this week.
28 September 2021
The 9th-floor slab is currently being cast and the brickwork is up to the 6th floor.
Plastering and skimming has begun on the 4th floor and the roof slab will be cast by year-end.
25 August 2021
We are 60% complete with the concrete structure and about to cast a portion of the 8th floor.
We have started brickwork on the 4th and 5th floors.
We are looking to finish the concrete structure by December 2021.
14 July 2021
9 June 2021